Almost one month ago, on March 19, I shared a T&G nickel gap progress report. Needless to say, I was bullish at the time. It had taken a while to make the transition to interior paneling, but once we started, I was optimistic that we’d make swift progress. That was then. It turns out that “nickel gapping” the walls and ceiling inside the icehouse would be intermittent and slower than anticipated.

Although most of the extended team has helped with nickel gapping the icehouse interior in one way or another, at one time or another, much of the recent progress has been made by Supi.